LOS ANGELES INTERNATIONAL AIRPORT (LAX)

Updated Runway Closure Schedule

February 2019

 

The current runway closure schedule has been updated to include additional closure dates for February 2019. The rest of the schedule remains the same. Please refer to the revised schedule below for further details. 

 

Thank you again for your understanding and patience during these runway closures.

 

Updated Runway Closure Schedule

Date

Runway

Time Period

Reason for Closure

Anticipated Change in Aircraft Operations

2/4 to 2/6

2/19 to 2/21

South Outboard Runway

25L/07R

12:30 AM – 6:30 AM

Maintenance

Deviation from Over-Ocean Operations

2/9 to 2/10

South Outboard Runway

25L/07R

2/9 1 PM – 2/10 8 AM

Extended Maintenance

Increase in outboard runway operations on South Complex and Deviation from Over-Ocean Operations

2/16 to 2/17

South Inboard Runway 25R/07L

2/16 1 PM – 2/17 8 AM

Extended Maintenance

Increase in outboard runway operations on South Complex and shift of some operations to North Complex

2/23 to 2/24

North Outboard Runway 24R/06L

2/23 1 PM – 2/24 8 AM

Extended Maintenance

Temporary change of runway for arrivals on North Complex and some shift of operations from North to South Complex

Note: Dates shown in blue represent additions to the schedule.

 


This email account is used for distributing information and is not monitored for incoming emails.

This message was sent from LAXFlightProcedures@lawa.org to LAXFlightProcedures@lawa.org
1 World Way, Los Angeles, CA, 90045


Update Profile/Email Address | Forward Email | Report Abuse